. Says all GenCos operating below capacity
. Says all GenCos operating below capacity
The Transmission Company of Nigeria (TCN), has attributed the current load shedding being experienced nationwide to very low power generation by the generation companies (GenCos) for TCN to wheel through the transmission grid to distribution companies nationwide.
This is even as it informed that not only are about 14 GenCos experiencing many challenges thereby limiting their output, all the companies are operating below capacity.
To this end, the General Manager, Public Affairs, TCN, Ndidi Mbah, described as “incorrect”, widely circulated media reports that it had reduced the load allocation to distribution companies (DisCos).
In a statement yesterday clarifying the situation to electricity consumers, Mbah said: “The correct position is that TCN can only transmit the quantum of power generated by GenCos through the national grid to distribution load centres nationwide.”
The statement further reads: “For clarity, TCN does not generate electricity and therefore can only transport cumulative generation from all the generation companies nationwide to distribution load centres.
“The distribution companies are responsible for end-users’ consumption. TCN allocates power to distribution companies based on approved percentage (formula approved by NERC), of the total generation available per hour or on day-ahead nomination.
“Presently, the cumulative generation nationwide is low and generation companies have attributed this to several factors including poor gas supply, fault in generating units of generating companies, scheduled and unscheduled maintenance, all of which have caused most power generating companies to limit their generation, and sometimes not generate at all.”
A combination of issues ranging from gas constraints, fault, and technical problems within generating plants caused persistent low generation and consequently low load allocation to distribution companies nationwide.
Troubled GenCos
Regarding the troubled Gencos, TCN said: “A summary of the power generating profiles in the last two months, for instance, clearly shows that 14 gas powered generating stations were either not generating at all or had limited generation at various times within the period.”
This, it said, further depleted the quantum of power generation available for transmission into the grid on a daily basis.
The Gencos affected include: Omotosho units 5 & 6; Olorunsogo units 3, 4 & 6; Omoku units 3 & 6; Omotosho NIPP units 3 & 4; and Delta units 15, 17, and 18;
Others are Afam VI units 11 & 12; Olorunsogo NIPP unit 3; Ihovbor NIPP unit 2; Sapele Steam unit 3; Sapele NIPP unit 1; Odukpani NIPP units 1 & 3; and Okpai units 11, 12 & 18.
TCN added that within the same period, Jebba Hydro and Shiroro Power Generating Stations were either out or had limited generation, causing additional loss of 232MW from the grid.
Furthermore, “other power generating plants such as Omotosho units 3&4, Olorunsogo units 1, Delta units 10 &20, Afam VI unit 13, Ihovbor NIPP units 4, Geregu NIPP units 22&23 and Odukpani NIPP units 2, 4 & 5, have also been out either on fault or for scheduled maintenance, causing a further loss of about 3,180MW from the grid.”
Balancing act
TCN further reiterates that a combination of issues ranging from gas constraints, fault, and technical problems within generating plants caused persistent low generation and consequently low load allocation to distribution companies nationwide.
“This is based on the fact that TCN can only transmit what is being generated by GenCos and presently they are all generating below capacity,” it said.
Given the above scenarios amid persistent low generation and attendant effect on the network, TCN said it has strived to dispatch available output “in a way that will not jeopardize the stability of the grid.”
“More recently, from the 1st to 4th of March, 2022, there was generation shortfall due to water management in Shiroro and Jebba hydro with the loss of 307MW and 125MW respectively from both stations.
“Within the same period, there were fault and technical problems in Egbin, causing 514MW shortfall and in Geregu causing 230MW shortfall, while reported fault at Alaoji NIPP reduced generation from the substation by 263MW,” the statement elaborated.
TCN can only transmit what is being generated by GenCos and presently they are all generating below capacity.
Gas shortages
TCN also said gas constraints alone in the Olorunsogo generating plant reduced generation from the station by 104MW, while Omotosho gas lost 102MW, and Sapele NIPP lost 263MW.
In Omotosho NIPP, there was a generation shortfall of 233MW and in Omoku a shortfall of 112MW. Two units in Okpai have limited generation due to technical problems causing a 204MW drop in generation and in Afam VI 511MW drop in generation.
Gas constraint and fault in Olorunsogo NIPP reduced generation by 240MW, Geregu NIPP by 435MW, and Ihovbor by 142MW. Also, due to gas pipeline pigging, Odukpani NIPP was SHUT DOWN which caused a reduction of generation by 575MW.
Noting that except cumulative power generation increases considerably for it to transmit to DisCos nationwide, TCN said it will be left with no choice than to continue to load shed.
“We will however continue to work hard to ensure the efficient allocation of the total load generated by power generating stations into the grid, bearing in mind the need to ensure that the national grid is stable in spite of the challenges posed by insufficient load on the transmission grid,” it concluded.