Power supply down by 676MW as TCN shuts down Egbin Power for repairs

Transmission lines

Power supply to some parts of the country has been disrupted following the shutdown of Egbin Power Plant for a three-day maintenance.

The shutdown led to the loss of 676 megawatts (MW) from the National Grid, as supply dropped from 4,416MW to 3,632MW.

A statement by the Transmission Company of Nigeria (TCN) posted on its verified X account (formerly Twitter) said the showdown was to allow Nigerian Gas Company to maintain the pipeline bringing gas into the plant.

The statement reads: “This is to notify the public that as at 11:13 hours of 18 December 2023, Egbin Power generating station was shut down to allow the Nigeria Gas Company (NGC) to maintain a linking gas pipeline supplying gas to Egbin Power Station.

“The station will be shut down for three days from today. This means a reduction of 676MW of bulk power generated into the nation’s grid for three days and consequently the quantum of bulk power available to be delivered to distribution companies load centres nationwide for the period.”

Aside from the Egbin maintenance, TCN’s wheeling capacity had been weaked due to a number of issues.

The station will be shut down for three days from today. This means a reduction of 676MW of bulk power generated into the nation’s grid for three days and consequently the quantum of bulk power available to be delivered to distribution companies load centres nationwide for the period.

A statement by the General Manager, Public Affairs, Ndidi Mbah, said TCN “maintenance crew is carrying out scheduled maintenance on its Keffi/Akwanga 132KV transmission line. The exercise is to enable them to replace broken 132kV Insulators.

“The maintenance commenced today, Monday,18th December, 2023, by 8.30 am to 5:30 pm for eight hours only.

“Keffi/Akwanga and its environs will be affected. Supply will be restored today”.

TCN had 24 hours earlier reported that at “about 7:57 pm on Saturday, 16th December 2023, there was a fire incident, following an explosion of capacitor voltage transformer on the Maryland-lkorodu 132/33kV transmission line 2.

“This necessitated the emergency opening of the substation at 7 58pm, which entailed the isolation of Maryland-llupeju 132kV line 1, which was the source of power supply to the substation.”

Mbah assured that “efforts were made to extinguish the fire but due to the presence of oil-immersed equipment within the surrounding area of the explosion it was difficult until the Lagos State Fire Service arrived at 8:45 pm and put out the fire completely at 8:55 pm. At 9:02 p.m., the same day, the substation was restored back into service.

It added that it was “diligently pursuing the reconductoring/rehabilitating of all its 132kV transmission lines and switchgears nationwide, which would greatly help eliminate such incidents.”

Total
0
Shares
Leave a Reply

Your email address will not be published. Required fields are marked *

Previous Post

FG, BoI to give N75bn loans to MSMEs in January 2024

Next Post

EU agrees new rules on hosting migrants, seeks to cut numbers

Related Posts
Total
0
Share