By Stanley Onyeka, Lagos
The Federal Competition and Consumer Protection Commission (FCCPC), has announced the sealing of Peachville Platinum Estate Limited, for failing to comply with a Compliance Notice issued in connection with a consumer complaint over the alleged non-delivery of a N140 million property in Abuja.
According to its statement, during the enforcement exercise conducted last Thursday, a team from the Commission, led by Marvin Nadah, sealed the company’s headquarters located along Airport Road, alongside its management office situated at Peachville Gardens, opposite Games Village, Abuja.
The complaint concerns a four-bedroom detached duplex with boys’ quarters at Peach Ville Estate, Phase II, Kukwaba District, Abuja.
The complainant told the Commission that they paid the full purchase price in August 2025 after the company assured them that it would hand over the property upon completion of payment. However, the property remained unfinished and was never handed over.
The Commission investigated the complaint and gave both parties an opportunity to present their accounts.
The company said the parties had agreed, at a meeting at the Federal Capital Territory Administration, that it would hand over the property by August 2026.
The company did not provide documents to support its account of the agreement.
When a developer accepts payment and commits to a handover date, the buyer is entitled to rely on that commitment.
Upon further proceedings and request to provide additional information, FCCPC noted that the company’s responses failed to satisfactorily address the issues the Commission raised. Its representatives also declined to sign the witness statements required to conclude the hearing.
The Commission issued a Compliance Notice on August 17, 2026, which it received on the 19th under Section 150 of the Federal Competition and Consumer Protection Act, 2018.
After confirming that the company had failed to comply within the stipulated period, the Commission took enforcement action under Section 150(4)(a) of the Act.
Commenting on the action, the Executive Vice Chairman and Chief Executive Officer of the FCCPC, Mr. Tunji Bello, said: “For many Nigerians, buying a home involves years of savings.
“When a developer accepts payment and commits to a handover date, the buyer is entitled to rely on that commitment.
“If delays arise, the developer should explain them promptly and give the buyer a realistic timetable.”